Проекти

Substation "University" - distribution substation №201, Substation "Teremkivska" - distribution substation № 67

Reconstruction of existing 10 kV cable lines:
• from 10 kV switchgear of "University" substation to 10kV switchgear of distribution substation №201 (2.4km) with a cable of the APvEgaPu-8.7/15-3 (1x500(g)/50) brand with a total length of 14500 m;
•from 10 kV switchgear of "Teremkivska" substation to 10kV switchgear of distribution substation №67 (3km) with a cable of the APvEgaPu-8.7/15-3 (1x500(g)/95) brand with a total length of 18100 m.