1. Power supply of the 10/0.4 kV transformer substation to be carried out by four 10 kV cable lines:
- from the switchgear 10 kV of transformer substation № 1966 and from the switchgear 10 kV of transformer substation № 2056 with a total route length of 1150 m.
- from the switchgear10 kV of transformer substation № 876 and from the switchgear 10 kV of transformer substation № 4334 with a total route length of 1400 m.
2. Laying of the 10 kV cable line from distribution substation № 210 to transformer substation № 4334 with a cable of the APvEgaPu brand -15 3(1x120(g)/50) with a length of 200 m.
3. Laying of 10 kV cable from transformer substation № 2009 to transformer substation № 2056, with cable brand APvEgaPu-15 3(1x120(g)/50) with a length of 195 m.
4. Installation of two power transformers with a capacity of 1000 kVA in transformer substation 10/0.4 kV.
5. Installation of equipment in switchgear10 kV and switchgear 0.4 kV.