Reconstruction of the 330 kV "Pivnichna" electrical substation:
Reconstruction of the 330 kV "Novokyivska" electrical substation:
Customer "Service for the Restoration and Development of Infrastructure in the Kyiv Region"
- busing of the 330/110 kV autotransformer;
- grounding;
- ventilation.
Reconstruction of the 330 kV "Novokyivska" electrical substation:
- busing of the 330/110 kV autotransformer;
- retrofit of the complete 35 kV transformer substation and the 0.4 kV self-service switchboard;
- installation of 35 kV disconnectors;
- laying of 35 kV cables;
- grounding;
- ventilation.
Customer "Service for the Restoration and Development of Infrastructure in the Kyiv Region"