The substation provides for the replacement of reinforced concrete portals open switchgear-330 kV and open switchgear-110 kV, respectively, in these places the planning of the territory is being carried out.
Portals 330 kV to be replaced:
P2SSH-330 №1;
P2SSH-330 №2;
P2SSH-330 №3;
P1SSH-330 №2;
P1SSH-330 №3;
PZF-330 №2.
In addition, the 330 kV cell portal is being dismantled.
Portals 110 kV to be replaced:
P-110 №10;
P-110 №1;
PZ-1;
PZ-0;
Construction conditions – Limited construction conditions. Construction and installation works are carried out on the territory of the operating substation.
Customer NPC "Ukrenergo"
Portals 330 kV to be replaced:
P2SSH-330 №1;
P2SSH-330 №2;
P2SSH-330 №3;
P1SSH-330 №2;
P1SSH-330 №3;
PZF-330 №2.
In addition, the 330 kV cell portal is being dismantled.
Portals 110 kV to be replaced:
P-110 №10;
P-110 №1;
PZ-1;
PZ-0;
Construction conditions – Limited construction conditions. Construction and installation works are carried out on the territory of the operating substation.
Customer NPC "Ukrenergo"