Construction of cogeneration gas piston plants at the Mykolaiv CHP

1. Development of design and estimate documentation for the Working Project stage:

  • passing a comprehensive state examination and obtaining a positive conclusion;
  • passing the environmental impact assessment procedure with obtaining a positive conclusion;
  • development and registration of a technical passport;
  • support in putting the facility into operation and obtaining a certificate of completion of the facility;
  • assignment of a legal address and registration of ownership of the facility

2. Implementation of a complex of construction and installation works:

  • construction of cogeneration gas piston plants based on 3 gas piston plants (GPP) manufactured by the Caterpillar XGC1900 type with a total electrical capacity of 5.7 MW (1.9 MW each) with waste heat boilers.
  • arrangement of external electrical and gas networks, including connection of a complex of cogeneration gas piston plants to electric and gas networks;
  • installation of heat utilizers;
  • connection of a complex of cogeneration gas piston plants to heat networks;
  • installation of a technical unit for metering gas, heat and electricity on the unit;
  • installation of a gas regulating point;
  • installation of ultrasonic meters with a volume conversion device to standard conditions.

The cogeneration gas piston complex is designed to meet its own needs and implement a parallel operation mode with the power system and operates in cogeneration mode: generation of electric energy together with generation of heat energy, which is simultaneously directed to heating the coolant in the heat network.

Customer PJSC "Mykolaivska Teploelektrotsentral"