1. Reconstruction of the 10kV cable line of the "Irpin" substation - Distribution Substation10kV №107 1/2 in the Bucha, Kyiv region:
2. Reconstruction of the 10kV cable line of the Distribution Substation №6-2A in the Fastiv, Kyiv region:
3. Reconstruction of the 10kV cable line of the "Irpin" substation - Distribution Substation 10kV №1/1- №1/2 in the Irpin, Kyiv region:
4. Reconstruction of the 10kV cable line for connecting to the electrical networks of electrical installations of residential buildings with built-in premises of a preschool institution for short-term care of children and construction of an underground parking lot in the Bucha, Kyiv region:
Customer PrJSC "DTEK Kyiv Regional Electric Networks"
- 22 wells were drilled using the HDD method with a total length of 737 m.
2. Reconstruction of the 10kV cable line of the Distribution Substation №6-2A in the Fastiv, Kyiv region:
- 4 wells were drilled using the HDD method with a total length of 195 m.
3. Reconstruction of the 10kV cable line of the "Irpin" substation - Distribution Substation 10kV №1/1- №1/2 in the Irpin, Kyiv region:
- 6 wells were drilled using the HDD method with a total length of 170 m.
4. Reconstruction of the 10kV cable line for connecting to the electrical networks of electrical installations of residential buildings with built-in premises of a preschool institution for short-term care of children and construction of an underground parking lot in the Bucha, Kyiv region:
- 3 wells were drilled using the HDD method with a total length of 146 m.
Customer PrJSC "DTEK Kyiv Regional Electric Networks"