Substation 110/6 kV "GPP"
According to the project and in accordance with the technical task, the following works were performed:
dismantling of the foundation of the T-1 transformer and oil receiver;
dismantling of the T-1 transformer;
arrangement of the foundation for the T-1 transformer and construction of a new oil drain;
replacement of power and control cables to T-1;
disassembly and assembly of disconnector RN-110;
re-installation of the 6 kV transmission line with a total length of 1 km.