This project provides for the following works:
  • dismantling of existing reactors. Construction of foundations and installation of new shunt reactors;
  • connection of the new reactor to the existing 750 kV busbar scheme;
  • construction of new foundations for the 750kV Surge Arrestor;
  • replacement of 750 kV Surge Arrestor;
  • installation of an automatic fire extinguishing controller based on the REQ650 company "ABB";
  • reconstruction of the existing reactor oil receiver;
  • replacement of reactor power and control cables;
  • construction of new fire protection walls. Reconstruction of the existing dry pipe lining of the reactor fire extinguishing system, with connection to the existing network;
  • partial reconstruction of the existing fire extinguishing automation of RSh-ZAES.

Customer NPC "Ukrenergo"