Construction of Cable line 110 kV from the "Ros" 110/35/10 kV substation to the "Fursy" 110/10 kV substation:
installation of a two-circuit cable line with a voltage of 110 kV from 3 single-wire cables for each circuit;
cables - insulated from cross-linked polyethylene of the APvEgaPu-110 brand with a section of 240 mm² with a copper screen with a section of 95 mm²;
laying FOCL with a single-mode cable for 24 fibers for the possibility of implementing telemechanization and technological communication.
The total length of the 110kV cable line is 6,580 m, of which 2,400 m was constructed using the horizontal direction drilling (HDD) method by the own installations.