Connection to the electrical network of a photovoltaic power station with a capacity of 6.8 MW

This project provided for the implementation of the following power supply works:

  • construction of two 10 kV cable lines to the switchgear10 kV of the substation 35/10 kV "Dimer" with a length of 4150 m;
  • reconstruction of existing reserve cells at the 35/10 kV "Dimer" substation to deliver generated power to the "Vyshgorod" Solar Power Plant;
  • installation of additional 10 kV cells and reconstruction of the existing one to connect compensating reactors;
  • installation of compensating reactors of the ONER3 OASC 200 kVA 10kV type complete with the REG-DPA unit;
  • construction of a new building for the substation telemechanics systems and complete reconstruction of the telemechanics system at the substation.