Проекти

Connection to the power grid of the office center

The project envisages:
1. The power supply of the 10/0.4 kV transformer substation will be provided by four 10 kV cable lines from the existing city networks.
2. Installation of two 1000 kVA power transformers in the 10/0.4 kV transformer substation.
3. Installation of equipment in switchgear 10 kV and in switchgear 0.4 kV.
2020-09-19 12:16 Projects