The project provides for the following works:
Phase A:
- replacement of crushed stone ballast of the oil receiver;
- restoration of the oil collection pit;
- replacement of the fire extinguishing system and supports;
- dismantling of the reactor and relocation to a storage area;
- arrangement of a temporary storage area for dismantled reactors;
- installation of the reactor and busbar connections;
- commissioning works.
Phase B:
- replacement of crushed stone ballast of the oil receiver;
- restoration of the oil collection pit;
- dismantling of the reactor and relocation to a temporary storage area;
- dismantling of R-50 rail tracks;
- replacement of NSP slabs;
- dismantling and subsequent installation of 110 kV bus support structures – 3 units;
- replacement of up to 35 kV cable in the channel – 283 m;
- replacement of the fire extinguishing system and supports;
- dismantling and subsequent installation of dry pipe support;
- replacement of the crossing over dry pipe PS-1;
- installation of the reactor and busbar connections;
- commissioning works.
Phase C:
- replacement of crushed stone ballast of the oil receiver;
- restoration of the dry pipe surface;
- oil filling with degassing;
- replacement of the cooler;
- installation of a 750 kV surge arrester;
- laying of cable for the fire extinguishing system;
- commissioning works;
- installation of a fire shield.
Client: NPC “Ukrenergo”