This project involves the following work:
- Dismantling of existing reactors. Construction of foundations and installation of new shunt reactors;
- Connection of the new reactor to the existing 750 kV busbar system;
- Construction of new foundations for the 750 kV switchgear;
- replacement of 750 kV oil-filled transformers;
- installation of an ABB REQ650-based automatic fire suppression controller;
- reconstruction of the existing reactor oil receiver;
- replacement of reactor power and control cables;
- construction of new fire protection walls. Reconstruction of the existing dry-pipe piping of the reactor fire suppression system, with connection to the existing network;
- partial reconstruction of the existing fire suppression automation system at the Zaporizhzhya NPP.
Client: NPC “Ukrenergo”