The substation plan calls for the replacement of the reinforced concrete portals for the 330 kV and 110 kV switchgear; accordingly, site preparation is underway at these locations.
330 kV portals to be replaced:
- P2SS-330 No. 1;
- P2SS-330 No. 2;
- P2SS-330 No. 3;
- P1SSH-330 No. 2;
- P1SSH-330 No. 3;
- PZF-330 No. 2.
In addition, the 330 kV cell portal is being dismantled.
110 kV portals to be replaced:
- P-110 No. 10 (portals opposite the ZPU);
- P-110 No. 11 (portals opposite the ZPU);
- PZ-0 (busbar bridge over the ZPU at VRU-110);
- PZ-0 (busbar bridge over the ZPU opposite).
Construction conditions – Restricted construction conditions. Construction and installation work is carried out on the territory of the operating substation.
Client: NPC “Ukrenergo”