Back to projects

110/6 kV Substation “GPP”

In accordance with the project and the technical specifications, the following work was performed:

  • demolition of the foundation for the T-1 transformer and the oil receiver;
  • demolition of the T-1 transformer;
  • construction of a foundation for transformer T-1 and construction of a new oil drain;
  • replacement of power and control cables to T-1;
  • dismantling and installation of disconnector RN-110;
  • re-routing of the 6 kV power line with a total length of 1 km.