This project involves the following work:
- construction of a 110 kV substation;
- re-routing of 110 kV cable sections from the “Nyvky-1 and -2” substations to the busbars of the “Mototsikletna” substation;
- dismantling of existing equipment;
- dismantling of reinforced concrete structures of the substation building;
- construction of a four-story enclosed 110/10 kV substation with a cable basement;
- installation of heating, ventilation, and air conditioning systems;
- installation of water supply and sewer systems, and fire protection systems;
- installation of main and auxiliary equipment for the 110/10 kV substation.
The following are subject to replacement:
- motor-operated disconnectors – 6 sets;
- isolators – 2 sets;
- 110 kV surge arresters – 6 sets;
- grounding switches with drives and surge arresters – 2 sets in power transformer circuits;
- power transformer T1 TRDCN-63000/110-U1 115+9×1.78%/10.5-10.5 kV.