Connection of a 6.8 MW photovoltaic power plant to the power grid

This project involved the following power supply works:

  • construction of two 10 kV cable lines to the 10 kV switchgear at the 35/10 kV “Dimer” substation, each 4,150 m long;
  • reconstruction of existing reserve bays at the 35/10 kV “Dimer” substation to deliver power generated by the “Vyshgorod” solar power plant;
  • installation of additional 10 kV bays and reconstruction of existing ones to connect compensating reactors;
  • installation of ONER3 OASC 200 kVA 10 kV shunt reactors complete with a REG-DPA unit;
  • construction of a new building for the substation’s telemetry systems and complete reconstruction of the telemetry system at the substation.