Connection to the electrical grid for the residential and office complex

Construction of a cable and pipe duct system (total of 11 chambers) and installation of 10 kV cable lines (from the distribution substation to substations No. 1, No. 2, No. 3, and No. 4) and 0.4 kV lines from substations No. 2 and No. 4 to the main distribution boards of residential buildings No. 2 and No. 4, boiler rooms 2 and 4 of the buildings to supply power to construction phases 1, 2, and 4.