The project provides for:
1. Powering the 10/0.4 kV substation via four 10 kV power cables from the city’s existing networks.
2. Installation of two 1,000 kVA power transformers in the 10/0.4 kV substation.
3. Installation of equipment in the 10 kV switchgear and in the 0.4 kV switchgear.