According to the project, the following work was performed:
- installation of 2 TMG-1000/10/0.4 kV power transformers;
- installation of a complete 0.4 kV switchgear equipped with 90-type switchgear compartments (9 units) in the existing OZTP-10/0.4 kV switchgear;
- installation of metering for the technical needs of the OZTP and at the 0.4 kV feeders in the RU-0.4 kV;
- construction of a 0.4 kV cable line from the 0.4 kV switchgear of the OZTP-10/0.4 kV to the 0.4 kV distribution points of residential buildings No. 1, No. 2, and No. 3.